Project Location
Grafton, Grand Forks, North Dakota
Certified Applicator
CSB Painting– Grafton, North Dakota
Owner
City of Grand Forks Wastewater Treatment Division
Engineering Firm
Webster, Foster, & Weston Consulting Engineers
Contractor
ICS, Inc
Products
Raven 155 at 8-10 mils DFT, applied in two wet-on-wet coats
Raven 405 at 90-110 mils DFT
Description of Application
The project was the lining of a new wastewater lift station structure, which was partially constructed from poured concrete and upper portion from precast concrete. This new structure was particularly challenging due to quick construction schedules. The poured concrete portion was approximately 14 days old, so Raven 155 WB Epoxy Primer was applied to the entire concrete surface to receive the lining system. The Raven 155 Primer allowed the structure to be coated prior to the 28-day minimum cure time required by most lining systems. The 155 also minimized outgassing of the new concrete, which was particularly troublesome on the roof & upper 10 feet. The following day the Raven 405 was applied in two applications approximately 2 hours apart, with the first 50 mil coat back troweled into the abrasive blasted surface to fill imperfections and eliminate remaining outgassing. The entire surface was checked for holidays/pinholes using high voltage holiday detection.