Manufacturer:
Raven Lining Systems
13105 E. 61st Street,
Suite A
Broken Arrow, OK 74012
(918) 615-0020
Location:
Romeoville, Illinois
Certified Applicator(s):
Kim Construction Company, Inc. has been in the sanitary sewer and manhole rehabilitation business since 1982. Over the past 32 years they have rehabilitated in excess of 50,000 manhole structures with various products and techniques.
Date of Project:
September 2014
Product(s):
Raven 405
Type of Structure(s):
Steel lift station
Condition of Structure(s):
Upon visually inspecting the lift station, it was discovered that the surface was heavily covered in rust.
Size/Cost:
Lift Station: 16’ diameter x 34’ deep; Valve Pit: 8’ diameter x 7’ deep
Description of Application:
Due to the size of the lift station, Kim Construction was only able to abrasion blast and coat 12’ VF at a time. If they chose to blast the entire structure at once, then they were worried the structure would flash rust, compromising the surface and possibly affecting the adhesion of the Raven 405. Also, due to the size of the lift station, the abrasion material had to be pumped out using the city of Romeoville’s vac-truck. Each 12’ VF blasted left about a 10-12 inches of rust and abrasion material on the bottom of the structure.